(9) Ointment/ Cream / Tooth Paste /Gel Manufacturing Automatic Process: |
|
|
Step:1 Water Phase: Fill D.M. water in water phase vessel than heated and stirring
(Water Phase Vessel with stirrer & jacketed) |
|
|
|
|
|
Step:2 Wax Phase: Fill wax in wax phase vessel than heated and stirring
(Wax Phase Vessel with stirrer & jacketed) |
|
|
|
|
|
Step:3 Melted wax and heated water will be transfer to in the Ointment/ Cream/ Tooth Paste/Gel Manufacturing Vessel by Vacuum Transfer system and mixed in the vessel. Than added drugs and ingredient with Heating, stirring and high speed homogenizer. Also the material re circulated in the vessel and Vacuumised for evaporate of the d (Machine –Ointment Manufacturing Jacketed Vessel with stirrer, High speed Homogenizer, Vacuum Pump and lid lifting system) |
|
|
|
|
|
Step:4 The material will be transfer to inh the storage tank by bump pump (M/c. Bump Pump) |
|
|
|
|
|
Step:5 The material will be store in the storage tank and this tank having facility for heating and trolley wheel for move to filling area.(Machine –Storage Tank) |
|
|
|
|
|
Step:6 The storage tank carry to filling machine by manually and the material will be heated by hot water circulation for easy transferring high viscous material by metering pump to the hopper of filling machine . (M/c- Metering Pump) |
|
|
|
|
|
Step:7 The Ointment/ Cream will be fill and seal by filling machine and packed by packing line machinery. (Machine –Filling & Sealing and Packing Line Machinery) |
|
|
|
|
|
Ointment / Cream will be packed by filling & sealing & packing line machinery |
|
|
|
|
|
Step: 8 Automatic washing of all vessel and Tank by CIP system (Machine –CIP/ WIP System) |
|
|
|
|
|
Please Note that the Triple Roller Mill will be used for proper mixing and reduced particle size of basic powder material and removing water and liquid content from final materials |
|
|
|
|